How To Get Electricity In Uganda

How To Get Electricity In Uganda

Electricity is a fundamental form of energy observable in positive and negative forms that occurs naturally (as in lightning) or is produced (as in a generator) and that is expressed in terms of the movement and interaction of electrons.

Steps To Get Electricity In Uganda

STEP 1

APPLICATION & REGISTRATION

Apply Online. Pay inspection fees through our payment channels (Mobile money & banks)

Step 2

INSPECTION

Upon payment of inspection fees, our team will visit you for inspection of premises within 2 days

STEP 3

PAYMENT & CONNECTION

Upon successful inspection, You will pay connection fees and a meter will be installed within 10-15 days upon receipt of payment by Umeme.

CONNECTION REQUIREMENTS

  • Copy of national ID or passport
  • Wiring certificate
  • Wayleave- permission from landowners through which the line will pass (if applicable)
  • Company seal and certificate of incorporation (for companies)
  • Trading license for sole proprietorships

STANDARD CHARGES

* See below definition of tariff types

Inspection Fees
DescriptionInspection Fees
a) Domestic / ResidentialUGX 41,300
b) Ordinary Commercial e.g. Shops/KiosksUGX 41,300
c) Three Phase – Time of UseUGX 88,500
d) Three phase – KVAUGX 118,000
1. New Connection Fees (Standard/ Single phase no pole and one pole connections)
Meter typeERA Approved VAT Incl costs (UGX)
a) Wireless split meter – No poleUGX 720,883
b) Bare Conductor Wireless split meter – One PoleUGX 2,387,472
c) ABC Conductor Wireless split meter – One PoleUGX 2,741,188
2. New Connection Fees (Non-standard and three phase connections)
New connection fees (Non-Standard Connection)Connection Fees Chargeable
a) 2 pole and more connections – single phaseCost after survey
b) Commercial-Three Phase (TOU)Cost after survey
c) Industrial – KVACost after survey

1. Domestic: LowVoltage supplied at 240 volts e.g.residential houses, salons, shops, kiosks etc.

2. Commercial: Single phase low voltage load e.g. supermarkets, restaurants, clinics etc.

3. Commercial: Three Phase low voltage below 100 Amperes e.g. small scale industries, fuel pumps, millers etc.

4. Industrial: Low & High voltage of 415 volts with maximum demand up to 500kVA and 11000 volts or 33,000 volts with maximum demand exceeding 500 kVA but up to 10,000 kVA respectively. Mainly used by large scale industries.